Before the renovation, learn to be lazy!
Home renovation natural to go to the building materials Museum to visit a few laps, today this series does not tell jokes, not wrangling, to give the public a real "decoration of the main material purchase order list", I am serious!
After the design plan is finalized , the owner must contact the cabinet company to confirm the position of the cabinet and the location of the kitchen electrical outlet; the designer, the owner, and the construction worker enter the bottom of the shop; the plumbers are positioning the line and open the slot; Electrician opened the trunk, began to order stoves, range hoods, water heaters, pans, squatting pans, toilets, wash basins, floor drains, power boxes.
After the completion of the trunking of the
water electrician, the time for opening the trunking is generally 2-3 days. After the completion of the trenching, the hydropower line starts to be installed. The owner begins to order wall and floor tiles and pulls the squat toilet to the site.

After the completion of the hydropower project (about one week or so), the mason's approach to the site is remodeled. At this time, the owner needs to pull the tiles to the site and schedule the door and door cover (mainly the size of the door).
After the masonry tiling project is completed, if the toilet needs to be partitioned or showered, the owner can inform them of the size of the arrival and begin production. 
Woodworker enters the field to start the ceiling construction or other woodworking production projects (need to contact the professional drilling hole, air conditioning vent hole).
Painters usually send wallpapers and reserve wallpapers when they enter the market because the wallpaper is generally delivered from the field.

After the painter's wall putty was scraped, the owner bought the aluminum buckle plate, the bathroom heater, the kitchen ceiling lamp, the exhaust fan, and the notification kitchen three-piece set to the site and installed it.

After the painter finishes the first pass of the primer, the owner needs to inform the installation of the door and door cover (the owner needs to purchase the hardware when installing the door. For example: lock, hinge, handle, etc.) If the kitchen or bathroom is a sliding door, Then, after the door covers are installed, it is necessary to make the sliding door size and start the production.
After the door is installed, the painter starts the latex paint after the base layer is completely processed and dried (if it is full-wall paper, the painter is informed to do the wallpaper basic layer processing). During the painting period (or during the wallpapering period) the owner needs to start purchasing the book. Wooden floors, lamps, curtains, pendants, etc., sanitary ware, switch panels.

After the painter is finished, the owner needs to pull lamps, pendants, fixtures, sanitary ware, and switch panels to the site for installation.
After the fixtures and fixtures are installed, the owner can notify the curtains, furniture, etc.
of the final process. pay attention:

1. The cabinet ordering can be scheduled early or the construction party enters the market three to five days before the order, because the cabinet water and electricity diagram is produced by the cabinet manufacturers (customized products require a period of about one month), the designer delivers the hydropower diagram to the owner's hands, so , will not delay the cable trunking. 2. Sanitary Ware Sanitary ware can be scheduled as early as possible or the construction party can enter the market three to five days before the order, because the plumber entering the market often needs to clean up the site, first change the drainage, and determine the size of the sanitary ware. 3. Wooden doors can be set early or the construction party enters the market three to five days before the purchase, this is a short or long main material distribution, short manufacturers, may be able to deliver half a month, long almost crossed half of the renovation period . It is also a fatal link to delay the duration of work. 4. Wall tiles can be scheduled as early as possible or the construction party enters the market three to five days before the purchase, general slusher probably arrived 10 days after the start. This time, you need to enter the wall and floor tiles. 5. Smoke stoves Smoke stoves should be considered when setting up the cabinets. Slotting of the cabinet countertops requires the size of the smoke oven. 6. Water Heater Water heater can be ordered as early as possible or when it is tiling. 7. Hardware This order is based on the amount of time provided by the carpenter. The general construction party will inform the owner 3 to 5 in advance. 8. Ceilings can be scheduled early or in the middle of the project, because the ceiling is mostly installed by the merchant, and it is completed after the wall tile is completed.
Basic Building Materials Buying Semi-packing Repair
Mattress Felt
Mattress Felt,Waterproof Mattress Felt,Custom Mattress Felt,Light Weight Mattress Felt
Suzhou Surface Protective New Material Technology Co.,Ltd , https://www.surfaceprotective.com